FPVC™ Installed via Pipe Bursting for Rehabilitation of Sanitary Sewer for Marina Coast Water District, Marina CA

In April 2007, Underground Solutions, Inc. (UGSI) contracted with Ventura Drilling to provide UGSI's FPVC™ pipe and fusion services for the rehabilitation of sanitary sewers for the Marina Coast Water District. Ventura Drilling was the pipe bursting subcontractor to Monterey Peninsula Engineering, the general contractor.

Pipeline Details and Project Summary
  • Project:
  • Location:
  • Length:
  • Pipe size:
  • Installation:
  • UGSI Contact:
  • Marina Sewer Improvement Project
  • Marina, CA
  • 1,700 LF
  • 10" and 12" DR25 FPVC™
  • Pipe Burst
  • Rob Craw (925) 577-7566 rcraw@undergroundsolutions.com

Both FPVC™ and HDPE were approved materials for this project. FPVC™ was selected because of its superior strength characteristics compared to HDPE, allowing Ventura Drilling to downsize from the 14" and 12" HDPE to 12" and 10" FPVC™, respectively. FPVC™ offered a reduced O.D. with equal or greater flow area at an equivalent pressure class compared to HDPE, reducing overall installation risk on the project.